Plan II from the September 1964 Interstate 266 study had the highway diverging from Interstate 66 east of the proposed overpass of Spout Run Parkway. Interstate 266 would then parallel Spout Run Parkway through the Spout Run Valley. A portion of Interstate 266 in this area would be in a tunnel. According to the document, the tunnel was proposed to help nullify potential community opposition and to help preserve the natural characteristics of the Spout Run area. After emerging from the tunnel, Interstate 266 would cross over the George Washington Memorial Parkway and the Potomac River on Three Sisters Bridge. The bridge would be named for Three Sisters Island which is located just north of the proposed crossing. An interchange at Georgetown University would provide downstream connections to the Potomac Freeway. Upstream connections would be provided to MacArthur Boulevard and Foxhall Road, both local streets. No upstream connections would be provided to the Potomac Freeway. The document noted these connections could be added for a nominal cost if needed. On the Virginia side, Interstate 266 traffic headed towards Interstate 266 could exit onto Spout Run Parkway.
This map details Plan II:
The 1964 Plan also included artists renderings of the proposals.
![]() |
|
Above: Plan II looking north towards
Washington, DC. Interstate 266 comes in from the lower left hand corner
of the picture. Georgetown University is at the top center of the
picture. The Potomac Freeway runs left to right in the top third of the
picture.
|
![]() |
Left: Plan II in the Spout Run Area
looking north towards Washington, DC. You can see Interstate 266 going
towards the top left of the picture as it goes through its tunnel in
the Spout Run Valley. Interstate 66 is coming from the bottom of the
picture and then turning right towards the top right. The road crossing
under Interstate 66 in the lower left of the picture is Lee Highway (US
29). The route going over Interstate 66 is an expanded Spout Run
Parkway. Key Bridge is barely visible in the extreme upper right of the
picture.
|
The summary of estimated costs for Plan II was as follows:
|
Item
|
Cost
|
|---|---|
| Approach - Virginia Side |
$16,790,000
|
| Approach - DC Side |
12,089,000
|
| Potomac River Bridge |
5,675,000
|
| Right of Way - Virginia Side |
10,379,000
|
| Right of Way - District Side |
8,302,000
|
| Contingencies at 10% |
5,414,000
|
|
================
|
|
| Grand Total |
57,679,000
|
Plan II with several modifications was studied further in 1973 as apart
of an Interstate 66 Corridor Study. The modifications are as follows:
Full details of the 1973 study along with map scans are on the main Unbuilt Interstate 266 page.